Iterating over OBX segments

Clovertech Forums Read Only Archives Cloverleaf Cloverleaf Iterating over OBX segments

  • Creator
    Topic
  • #50053
    Gary Atkinson
    Participant

      I am trying to iterate over over the path:

          1(0).1(0).1(0).OBX —> 1(0).OBX

      I am using the 2.3 standard ORU inbound variant.  I can not seem to copy over more than 1 OBX segment.  When I set-up the Iterate in the xlate where do I put the %g1?  I tried vary places and I can not seem to get it to work.

    Viewing 2 reply threads
    • Author
      Replies
      • #64692
        Tom Rioux
        Participant

          If I am ever unsure where to put the % variable, I just run my message through the variant in the HL7 tester and select “Detail Level 2” or higher.  That should show you were to put the variable.

          Thanks…Tom

        • #64693
          Scott Folley
          Participant

            You said what the inbound variant was but you did not say what the outbound variant was.

          • #64694
            Gary Atkinson
            Participant

              My problem was how I had my basis set in the iteration.  After a conversation with Jim he set me straight.  I was manually adding in my basis and did not know that translation tool could do it for you  ðŸ˜® .  The outbound variant is also 2.3, but someone else customized it.  The OBX and OBR are placed in group 1.  Once I corrected the basis, all OBX segments parsed out.

          Viewing 2 reply threads